AN APPRAISAL OF FACTORS AFFECTING THE ACCURACY OF COST PLANNING FOR BUILDING PROJECTS IN NIGERIA


AN APPRAISAL OF FACTORS AFFECTING THE ACCURACY OF COST PLANNING FOR BUILDING PROJECTS IN NIGERIA

ABSTRACT

The importance of accurate estimates during the early stages of cost planning of capital projects has been widely recognized for many years. Even so, very few quantitative methods are available that enable estimators and business managers to objectively evaluate the accuracy of early estimates and planning.

The primary purpose of this study was to identify and examine the factors affecting accuracy of cost planning of building projects as it relate to the Nigerian construction industry. To accomplish this aim, quantitative data were collected from consultant Quantity Surveyors. Each of the respondents was asked to assign a one-to-ten rating for each of 10 potential drivers of estimate accuracy for a given estimate. The data were analyzed using simple statistical tools which include; mean, standard deviations and percentages were used to represent the information.  The study analysis identified 5 of the 10 factors that were most significant at the  level. In this finding the five factors, in order of significance were, Amount of information available, Time allowed to prepare the estimate, Experience of the consultant team, Complexity of the project, and bidding and Suitability/stability of the market.

Cost estimating and planning is a fundamental part of the construction industry. The success or failure of a project is dependent on the accuracy of several estimates through-out the course of the project. Construction estimating is the compilation and analysis of many items that influence and contribute to the cost of a project. Estimating which is done before the physical performance of the work requires a detailed study and careful analysis of the bidding documents, in order to achieve the most accurate estimate possible of the probable cost consistent with the bidding time available and the accuracy and completeness of the information submitted. Overestimated or underestimated cost has the potential to cause loss to local contracting companies.

                  TABLE OF CONTENTS

Title page………………………………………….……………………………………………i

Declaration…………………………………………….………………………………………ii

Certification………………………………………………….……………………………….iii

Dedication…………………………………………………………………………………….iv

Acknowledgement………………………………………………………………………….….v

Abstract………………………………………………………………………………………vii

Table of content…………………………………………………..…………………………viii

Table of figures……………………………………………………………………………….ix

List of tables……………………………………………………………………….…………..x

CHAPTER ONE

1.1  INTRODUCTION………………………………………………...………………….….1

1.2  Statement of the problem…………………………………………..…………………..…3

1.3.0  Aim and objectives…………………………………………..………………………….4

1.3.1  Aim………………………………………………………….…………………………..4

1.3.2  Objectives………………………………………………………….....…………………4

1.4.0  Scope and limitation……………………………………………...……………………..4

1.4.1  Scope…………………………………………………………………………...…….…4

1.4.2  Limitation…………………………………………..……………………………..…….5

CHAPTER TWO

2.0               LITERATURE REVIEW………………………………………..…………….…...…6

2.1.1        Cost planning………………………………………………………………...……...…6

2.1.2      History and Development of cost planning…………………………….…..……...…6

2.2.0        Cost control………………………………………………………………….……..….7

2.21           Definition………………………………………………………………………….….7

2.2.2        Cost plan………………………………………………………….……………………8

2.3              Approximate estimating………………………………….……………...…………….8

2.4.0     Concept of cost planning………………………………………………………..…….9

2.4.1        Preliminary cost planning ………………………………………..…………………..10

2.4.2        Cost planning reports…………………………………………..………………….…10

2.5.0        Cost Planning techniques/methods………………………………………………..….12

2.5.1        Various cost planning techniques……………………………………………...……..12

1.5.1.1  Easy cost planning (ECP)……………………………………………………………12

2.5.1.2  Network costing………………………………………………………………….….13

2.5.1.3  Detailed costing………………………………………….…………………………..13

2.5.1.4 Unit costing……………………………………………………………….………….14

2.5.2        Elemental cost planning…………………………………………………………...…14

2.5.3        Comparative cost planning……………………………………………………..…….15

2.6              Uses of cost planning………………………………………….…………..…………15

2.7              Factors affecting the accuracy of cost planning………………...……………………16

2.7.1        Location factor……………………………………………………………….………16

2.7.2        Design factor…………………………………………………………….…………...17

2.7.3        Qualitative factor…………………………………………………………..…………19

2.7.4        Construction factor…………………………………………….……………………..19

2.7.5        Time factor……………………………………………..……………………….……19

2.7.5.1  Project complexity……………………………………………………………………20

2.7.5.2  Availability/amount of project information…………………………….……………20

2.7.5.3  Technological factor………………………………………………………….………21

2.7.5.4  Contract requirements/stage of work………………………………...………………21

2.7.5.5  Team’s/contractor’s/consultant’s experience and efficiency……….………………..21

2.7.5.6  Stability of market/market requirement………………………………...……………21

CHAPTER THREE

3.0     RESEARCH METHOD………..……………………………………………...………25

3.1     Population and sample………………………………………………………………....25

3.2     Survey method……………………………………………………………………….…26

CHAPTER FOUR

4.0     DATA PRESENTATION, ANALYSIS AND INTERPRETATION………………..28

4.1     Data collection…………………………………………………………...……..………28

4.2     Data presentation and analysis……………………………....………………..………..30

CHAPTER FIVE

5.0    CONCLUSION AND RECOMMENDATION………….……………………....…….50

5.1    Conclusion………………………………………………………………………..……..50

5.2    Recommendation………………………………………….…………………….………52

References and Bibliography………………………………………………………………...54

APPENDICES

APPENDIX I………………………………………………………….………………..……59

LIST OF TABLES

Table 4.1.0: Description of data collection from questionnaire survey28

Table 4.2.0: Summary of results’ table showing how often the respondents prepare cost plans for building, civil engineering, heavy engineering, and services works

Table 4.2.1: Percentage ranking of work type showing how often the respondents prepare cost plans for building, civil engineering, heavy engineering, and services works…………………………………………….33

Table 4.2.2: Respondents' preparation of cost plans for their organization……………………………………35

Table 4.2.3: percentage of building projects handled in which cost plans were prepared by  respondents………………………………...36

Table 4.2.4: Method(s) used for preparation of cost planning………………………………………………………….37

Table 4.2.5: Cost planning method(s) that is/are mostly used in the respondents' organization………38

Table 4.2.6: Respondents’ reason for choosing a given cost planning method(s)

Table 4.2.7: Urgency of demand for cost plans when commissioned

Table4.2. 8: Adequacy of time to meet ClientsDemand for cost plans

Table 4.2.9: Source of Data mostly Used for Cost Planning

Table 4.2.10: Accuracy and Reliability of Cost Plans being Used

Table 4.2.11: Factors that affect the accuracy of cost planning of building projects

Table 4.2.12: Mean score and standard deviation for factors affecting cost planning of building projects in Nigeria              

CHAPTER ONE

INTRODUCTION

1.1              BACKGROUND OF THE STUDY

Costing in building construction is the application of price to schedules of item of labour and materials in order to obtain an approximation of cost of construction project (Ibrahim, 2004).

Cost planning of construction project is concerned with keeping the cost within a predetermined cost estimate during the pre-contract and post-contract stages of the construction works. The process of pre-contract cost planning involves the preparation of an approximate estimate amongst others. The object of the approximate is to provide an estimate of a probable cost of a project before detail design or post-contract service (Hoer, 1997).

Today’s client needs are becoming more sophisticated and complicated leading to difficulties in estimating the probable cost of construction works. The clients themselves are becoming more sophisticated in the level of in-house technical expertise and techniques available to them and they in turn expect a high level of efficiency, accuracy and expertise from their professionals. The introduction of new construction methods, materials and systems create greater difficulties in assessing and planning for the capital and maintenance cost of construction.

Adams (1999) reported that cost planning has become more sophisticated over the last decade and is increasingly becoming a service that the employer is expecting from the Quantity Surveyor to ensure that he receives better value for money and the project cost is kept within the budget.

Cost planning of construction projects is aimed at ensuring that the resources are used to the best advantage amidst alternating high cost of construction resources and acute shortage of funds as clients increasingly insists on project designs to be executed in a way to give them better value for money when completed.

However, there are several factors that may affect the efficiency of cost planning at different stages of the project; from the pre-contract through the post-contract stage. Although, careful detailed order of work will definitely reduce these effects that lead to the large discrepancies between the tender figures and final cost of the construction.

The accuracy of cost planning is measured by how well the estimated cost can be compared to the actual construction cost (Oberleder and Trost, 2002).

            Hore (1997) stated that the level of accuracy of a cost plan depends upon the level of information availability at time of preparation.

Pre-tender cost estimating and planning of building projects requires extensive knowledge and expertise. Due to inadequate design information in the early design stages, it is extremely difficult for Quantity Surveyors to arrive at accurate cost estimates and cost planning becomes inefficient (Koleola and Henry 2008).

According to Koloela and Henry (2008), there are seven most important factors, based on the construction industry experience of the Quantity Surveyors which affect the accuracy of pre-tender cost planning.

The seven most important factors as highlighted by Koloela and Henry are; expertise of consultants, Quality of information and flow requirements, project team’s experience of the type of construction, tender period and market condition, extend of completion of pre-tender designs, complexity of design and construction, availability and supply of labour and materials.

Taking these factors into consideration at project inception stage could improve the accuracy of the preliminary cost advice consultant quantity Surveyors give their clients.

1.2               STATEMENT OF THE RESEARCH PROBLEM

It has been discovered that in practice, contractors device their own methods of cost planning and bidding and the accuracy of their methods is doubtful (Akintoye, and Fitzgerald 1999 citing Law, 1994). The importance of accurate estimates during the early stages of capital projects has been widely recognized for many years. Early project estimates represent a key ingredient in business unit decisions and often become the basis for a project's ultimate funding. However, a stark contrast arises when comparing the importance of early estimates with the amount of information typically available during the preparation of an early estimate. Such limited scope definition often leads to questionable estimate accuracy. Even so, very few quantitative methods are available that enable estimators and business managers to objectively evaluate the accuracy of early estimates. The problem here is how to establish such a model to assess the factors affecting the accuracy of cost planning. To accomplish this, quantitative data were collected from consultant Quantity Surveyors from the construction industry.

.

AN APPRAISAL OF FACTORS AFFECTING THE ACCURACY OF COST PLANNING FOR BUILDING PROJECTS IN NIGERIA



TYPE IN YOUR TOPIC AND CLICK SEARCH.






RESEARCHWAP.ORG
Researchwap.org is an online repository for free project topics and research materials, articles and custom writing of research works. We’re an online resource centre that provides a vast database for students to access numerous research project topics and materials. Researchwap.org guides and assist Postgraduate, Undergraduate and Final Year Students with well researched and quality project topics, topic ideas, research guides and project materials. We’re reliable and trustworthy, and we really understand what is called “time factor”, that is why we’ve simplified the process so that students can get their research projects ready on time. Our platform provides more educational services, such as hiring a writer, research analysis, and software for computer science research and we also seriously adhere to a timely delivery.

TESTIMONIES FROM OUR CLIENTS


Please feel free to carefully review some written and captured responses from our satisfied clients.

  • "Exceptionally outstanding. Highly recommend for all who wish to have effective and excellent project defence. Easily Accessable, Affordable, Effective and effective."

    Debby Henry George, Massachusetts Institute of Technology (MIT), Cambridge, USA.
  • "I saw this website on facebook page and I did not even bother since I was in a hurry to complete my project. But I am totally amazed that when I visited the website and saw the topic I was looking for and I decided to give a try and now I have received it within an hour after ordering the material. Am grateful guys!"

    Hilary Yusuf, United States International University Africa, Nairobi, Kenya.
  • "Researchwap.org is a website I recommend to all student and researchers within and outside the country. The web owners are doing great job and I appreciate them for that. Once again, thank you very much "researchwap.org" and God bless you and your business! ."

    Debby Henry George, Massachusetts Institute of Technology (MIT), Cambridge, USA.
  • "Great User Experience, Nice flows and Superb functionalities.The app is indeed a great tech innovation for greasing the wheels of final year, research and other pedagogical related project works. A trial would definitely convince you."

    Lamilare Valentine, Kwame Nkrumah University, Kumasi, Ghana.
  • "I love what you guys are doing, your material guided me well through my research. Thank you for helping me achieve academic success."

    Sampson, University of Nigeria, Nsukka.
  • "researchwap.com is God-sent! I got good grades in my seminar and project with the help of your service, thank you soooooo much."

    Cynthia, Akwa Ibom State University .
  • "Sorry, it was in my spam folder all along, I should have looked it up properly first. Please keep up the good work, your team is quite commited. Am grateful...I will certainly refer my friends too."

    Elizabeth, Obafemi Awolowo University
  • "Am happy the defense went well, thanks to your articles. I may not be able to express how grateful I am for all your assistance, but on my honour, I owe you guys a good number of referrals. Thank you once again."

    Ali Olanrewaju, Lagos State University.
  • "My Dear Researchwap, initially I never believed one can actually do honest business transactions with Nigerians online until i stumbled into your website. You have broken a new legacy of record as far as am concerned. Keep up the good work!"

    Willie Ekereobong, University of Port Harcourt.
  • "WOW, SO IT'S TRUE??!! I can't believe I got this quality work for just 3k...I thought it was scam ooo. I wouldn't mind if it goes for over 5k, its worth it. Thank you!"

    Theressa, Igbinedion University.
  • "I did not see my project topic on your website so I decided to call your customer care number, the attention I got was epic! I got help from the beginning to the end of my project in just 3 days, they even taught me how to defend my project and I got a 'B' at the end. Thank you so much researchwap.com, infact, I owe my graduating well today to you guys...."

    Joseph, Abia state Polytechnic.
  • "My friend told me about ResearchWap website, I doubted her until I saw her receive her full project in less than 15 miniutes, I tried mine too and got it same, right now, am telling everyone in my school about researchwap.com, no one has to suffer any more writing their project. Thank you for making life easy for me and my fellow students... Keep up the good work"

    Christiana, Landmark University .
  • "I wish I knew you guys when I wrote my first degree project, it took so much time and effort then. Now, with just a click of a button, I got my complete project in less than 15 minutes. You guys are too amazing!."

    Musa, Federal University of Technology Minna
  • "I was scared at first when I saw your website but I decided to risk my last 3k and surprisingly I got my complete project in my email box instantly. This is so nice!!!."

    Ali Obafemi, Ibrahim Badamasi Babangida University, Niger State.
  • To contribute to our success story, send us a feedback or please kindly call 2348037664978.
    Then your comment and contact will be published here also with your consent.

    Thank you for choosing researchwap.com.