AN INVESTIGATION INTO RISK MANAGEMENT PRACTICES AMONGST QUANTITY SURVEYORS IN THE CONSTRUCTION INDUSTRY OF NIGERIA


AN INVESTIGATION INTO RISK MANAGEMENT PRACTICES AMONGST QUANTITY SURVEYORS IN THE CONSTRUCTION INDUSTRY OF NIGERIA    

TABLE OF CONTENT

Title Page………………..i

Certification………….…ii

Dedication………………iii

Acknowledgement……….iv

Table of content……...…v

CHAPTER ONE: INTRODUCTION

1.1 background of the study

1.2 statement of the problem

1.3 objectives of the study

1.4 research questions

1.5 research hypothesis

1.6 significance of the study

1.7 scope and limitation of study

1.8 definition of terms

CHAPTER TWO: LITERATURE REVIEW

2.0 introduction

2.1 risk and risk management

2.1.1 definition of risk

2.1.2 classification of risk in construction

2.2 theoretical framework

2.2.1 Project life cycle

2.2.2 Planning and design phase

2.2.3 Contractor selection phase

2.2.4 Project mobilization phase

2.1.5 Project operation phase

2.2.6 Project close-out and termination phase

2.2.7 Risks in the PLC

2.3 the role of the quantity surveyor in project Management

2.3.1 Decision-making process from risk management perspective

2.4 the risk management

2.4.1 Risk definition

2.4.2 A concept of risk management

2.4.3 Benefits with risk management

2.4.4 Limits of risk management

2.4.5 Risks in construction projects

2.5 the risk management process

2.5.1 Risk identification

2.5.2 Assessment/analysis

2.5.2.1 Quantitative methods

2.5.2.2 Qualitative methods

CHAPTER THREE: RESEARCH METHODOLOGY

3.0 introduction

3.1 research design

3.2 population of the study

3.3 sample and sampling technique

3.4 research instrument

3.5 validation of an instrument

3.6 method of data analysis

CHAPTER FOUR: DATA ANALYSIS AND INTERPRETATION OF RESULTS

4.1    Introduction

Analysis of research questions

Analysis of research hypothesis

CHAPTER FIVE: SUMMARY, CONCLUSIONS AND RECOMMENDATIONS

5.1    Summary

5.2    Recommendations

5.3    Conclusion

References

Appendix

Questionnaire            

CHAPTER ONE

INTRODUCTION

1.1 BACKGROUND OF THE STUDY:

Quantity surveying is concerned with controlling and managing construction projects. The Nigerian construction industry is faced with uncertainties. With construction targets not being met and high rate of abandoned construction projects, there is great need for proper risk assessment and implementation. Managing risks in construction projects have been recognized as a very important process in order to achieve project objectives in terms of time, cost, quality, safety and environmental sustainability (Mills, 2001). Project risk management is an iterative process: the process is beneficial when is implemented in a systematic manner throughout the lifecycle of a construction project, from the planning stage to completion.

Risk management has become an integral process in managing construction projects. Construction project activities are to be well calculated in-order for the deliverable to be of great use and benefit to its stakeholders. To complete most construction projects on time, minimizing cost and wastages proper risk management techniques must be employed (Tchankova, 2002). According to Mills (2001), systematic risk management is expecting the unexpected or in other words it is a tool which helps control risks in construction projects and its objective is to introduce a simple, practical method of identifying, assessing, monitoring and managing risk in an informed and structured way. 

Normally, in risk management process, the first steps will involves risk identification process which includes the prioritization process in order to identify and rank the risk based on its impact and seriousness. Risk that will have a greater impact on a project normally will be handled first and low impact risk will be handled later. 

Construction project team consist of professional such as the architect, engineer, and the quantity surveyor that will help to assist and advice the client in order to meet all the project objectives in term of time, quality and cost. Awareness and knowledge on risk management is very crucial so that they will deal with the risk properly which will directly leads to project success. Due to this scenario, this research aims to identify the level of awareness of construction professional specifically Nigerian quantity surveyors towards risk management. Apart from that, it will also aim to identify how risk management being implemented in the Nigerian construction industry and also the potential barrier and challengers in the implementation of risk management specifically from the quantity surveyor's point of view.

1.2 STATEMENT OF THE PROBLEM

Embarking on a construction project involves taking risks, as the Nigerian construction industry is not risk-free. No matter how small or simple is the project it is still can go wrong as soon as the two parties, the employer and the contractor signed a contract they have taken onboard the risk (Sawczuk, 1996). The individual in the construction industries that undertake various activities are heterogeneous since client, consultant and contractors have different roles and objectives (flanagan, 1995). Risk management in Nigerian construction industry is actually not widely being practiced. 

According to Burchett (2009), Risk in construction, however cannot be eliminated, but it can be minimized, transferred or retained. However, the industry has a very poor reputation for managing risk, with many projects failing to meet deadlines and cost argents (Mills, 2001). In practice, normally in order to deal with the unexpected event, there will be an allocation about 10 percent from the estimated cost of the proposed construction project as a contingency sum. Earlier observation shows that the risk management process is not widely being implemented in Nigerian construction industry. For this reason, this research seeks to identify the barriers and challenges for the implementation of risk management in the Nigerian construction industry.

1.3 OBJECTIVES OF THE STUDY:

The aim of this research is to investigate the practice of risk management amongst the construction practitioners specifically the quantity surveyor in the Nigerian construction industry.

In order to achieve the aim of the study, specific objectives for the study are:

To evaluate the quantity surveyor's level of awareness and acceptance on Risk Management practice. To identify the current practice of risk management amongst Quantity Surveyors’. To examine the barriers and challenges to the implementation of risk management in construction project from the quantity surveyor's point of view.

1.4 RESEARCH QUESTIONS

What is the quantity surveyor's level of awareness and acceptance on Risk Management practice? What is the current practice of risk management amongst Quantity Surveyors’? What barriers and challenges face the implementation of risk management in construction project from the quantity surveyor's point of view?

1.5 RESEARCH HYPOTHESIS

Ho: Awareness and acceptance of risk management practices do not aid quantity surveyors in attaining contruction project objectives Hi: Awareness and acceptance of risk management practices aid quantity surveyors in attaining construction project objectives

1.6 SIGNIFICANCE OF THE STUDY: 

Findings of this study will aid Nigerian quantity surveyors in appreciating the importance of adopting proper risk management techniques in their daily jobs. Since risk management is not widely being adopted in Nigerian construction industry, this research will help to promote the practice of risk management among the industry's players.

In addition to this, being an inter-discipline type of research, both the consultants and contractors and also the industry as a whole may benefit from the outcome of the research and have better understanding on risk management.

1.7 SCOPE AND LIMITATION OF STUDY:  

This research study will focus on risk management practices adopted by quantity surveyors in Uyo Local Government area of Akwa Ibom State, Nigeria. All findings and recommendations from the study are limited to findings and recommendations based on the chosen sample size.

In carrying out this study, the researcher was faced with time and finance constraints, as lectures did not give room for more time to extend the research time frame. Finance on the other hand made printing, transportation to cover a wider area difficult.

1.8 DEFINITION OF TERMS

RISK- This is the potential of losing something of value, weighed against the potential to gain something of value. 

RISK PERCEPTION- Risk perception is the subjective judgment people make about the severity of a risk, and may vary person to person 

PRACTICE- is the act of rehearsing a behavior over and over, or engaging in an activity again and again, for the purpose of improving or mastering it, as in the phrase "practice makes perfect 

QUANTITY SURVEYOR- a Quantity Surveyor (QS) is a professional working within the construction industry concerned with construction costs and contracts. 

CONSTRUCTION- In the fields of architecture and civil engineering, construction is a process that consists of the building or assembling of infrastructure. Far from being a single activity, large scale construction is a feat of human multitasking. Normally, the job is managed by a project manager, and supervised by a construction manager, design engineer, construction engineer or project architect.

RISK MANAGEMNENT- is the identification, assessment, and prioritization of risks followed by coordinated and economical application of resources to minimize, monitor, and control the probability and/or impact of unfortunate events or to maximize the realization of opportunities.

.

AN INVESTIGATION INTO RISK MANAGEMENT PRACTICES AMONGST QUANTITY SURVEYORS IN THE CONSTRUCTION INDUSTRY OF NIGERIA



TYPE IN YOUR TOPIC AND CLICK SEARCH.






RESEARCHWAP.ORG

Researchwap.org is an online repository for free project topics and research materials, articles and custom writing of research works. We’re an online resource centre that provides a vast database for students to access numerous research project topics and materials. Researchwap.org guides and assist Postgraduate, Undergraduate and Final Year Students with well researched and quality project topics, topic ideas, research guides and project materials. We’re reliable and trustworthy, and we really understand what is called “time factor”, that is why we’ve simplified the process so that students can get their research projects ready on time. Our platform provides more educational services, such as hiring a writer, research analysis, and software for computer science research and we also seriously adhere to a timely delivery.

TESTIMONIES FROM OUR CLIENTS


Please feel free to carefully review some written and captured responses from our satisfied clients.

  • "Exceptionally outstanding. Highly recommend for all who wish to have effective and excellent project defence. Easily Accessable, Affordable, Effective and effective."

    Debby Henry George, Massachusetts Institute of Technology (MIT), Cambridge, USA.
  • "I saw this website on facebook page and I did not even bother since I was in a hurry to complete my project. But I am totally amazed that when I visited the website and saw the topic I was looking for and I decided to give a try and now I have received it within an hour after ordering the material. Am grateful guys!"

    Hilary Yusuf, United States International University Africa, Nairobi, Kenya.
  • "Researchwap.org is a website I recommend to all student and researchers within and outside the country. The web owners are doing great job and I appreciate them for that. Once again, thank you very much "researchwap.org" and God bless you and your business! ."

    Debby Henry George, Massachusetts Institute of Technology (MIT), Cambridge, USA.
  • "Great User Experience, Nice flows and Superb functionalities.The app is indeed a great tech innovation for greasing the wheels of final year, research and other pedagogical related project works. A trial would definitely convince you."

    Lamilare Valentine, Kwame Nkrumah University, Kumasi, Ghana.
  • "I love what you guys are doing, your material guided me well through my research. Thank you for helping me achieve academic success."

    Sampson, University of Nigeria, Nsukka.
  • "researchwap.com is God-sent! I got good grades in my seminar and project with the help of your service, thank you soooooo much."

    Cynthia, Akwa Ibom State University .
  • "Sorry, it was in my spam folder all along, I should have looked it up properly first. Please keep up the good work, your team is quite commited. Am grateful...I will certainly refer my friends too."

    Elizabeth, Obafemi Awolowo University
  • "Am happy the defense went well, thanks to your articles. I may not be able to express how grateful I am for all your assistance, but on my honour, I owe you guys a good number of referrals. Thank you once again."

    Ali Olanrewaju, Lagos State University.
  • "My Dear Researchwap, initially I never believed one can actually do honest business transactions with Nigerians online until i stumbled into your website. You have broken a new legacy of record as far as am concerned. Keep up the good work!"

    Willie Ekereobong, University of Port Harcourt.
  • "WOW, SO IT'S TRUE??!! I can't believe I got this quality work for just 3k...I thought it was scam ooo. I wouldn't mind if it goes for over 5k, its worth it. Thank you!"

    Theressa, Igbinedion University.
  • "I did not see my project topic on your website so I decided to call your customer care number, the attention I got was epic! I got help from the beginning to the end of my project in just 3 days, they even taught me how to defend my project and I got a 'B' at the end. Thank you so much researchwap.com, infact, I owe my graduating well today to you guys...."

    Joseph, Abia state Polytechnic.
  • "My friend told me about ResearchWap website, I doubted her until I saw her receive her full project in less than 15 miniutes, I tried mine too and got it same, right now, am telling everyone in my school about researchwap.com, no one has to suffer any more writing their project. Thank you for making life easy for me and my fellow students... Keep up the good work"

    Christiana, Landmark University .
  • "I wish I knew you guys when I wrote my first degree project, it took so much time and effort then. Now, with just a click of a button, I got my complete project in less than 15 minutes. You guys are too amazing!."

    Musa, Federal University of Technology Minna
  • "I was scared at first when I saw your website but I decided to risk my last 3k and surprisingly I got my complete project in my email box instantly. This is so nice!!!."

    Ali Obafemi, Ibrahim Badamasi Babangida University, Niger State.
  • To contribute to our success story, send us a feedback or please kindly call 2348037664978.
    Then your comment and contact will be published here also with your consent.

    Thank you for choosing researchwap.com.